Short answer for investors

Legal due diligence checklist for Romanian renewable energy projects, covering SPV, land, permitting, ATR, grid connection, ANRE, contracts, financing and bankability.

Why this matters in practice

Romanian renewable energy due diligence in 2026 should test whether a project is legally buildable, grid-real, financeable, operable and monetisable, not merely whether it has a promising document list.

Executive answer

Romanian renewable energy due diligence in 2026 should test whether a project is legally buildable, grid-real, financeable, operable and monetisable, not merely whether it has a promising document list.

Legal Due Diligence for Renewable Energy Projects in Romania Practical 2026 Romanian analysis

Investor reading map

First questionIs the project a real legal energy asset or only a development story?
Second questionWhich risks affect buildability, financing or transferability?
Third questionWhat must be reflected in price, conditions precedent, warranties or indemnities?

1. Why legal DD in Romania has changed

Until recently, many renewable energy deals in Romania were sold on a simple story: “we have land, CU, ATR, maybe building permit; therefore the project is RTB.” In 2026, that is no longer enough.

Romania has a very large renewable pipeline on paper. According to data reported from ANRE as of 1 March 2026, there were 1,431 renewable projects with valid ATRs / grid connection approvals, totalling 81,322 MW, but only a much smaller part was in an advanced stage: 871 projects with signed grid connection agreements, 595 projects with grid connection agreements and building permits, and 193 projects with building permits and ANRE establishment authorisations. For 2026 specifically, ANRE indicated 107 advanced projects totalling 3,843 MW expected to reach COD.

That is the background. Romania does not have a lack of “projects”. It has a shortage of bankable, buildable, grid-real projects. This is why a Romanian renewable DD in 2026 must answer one central question:

Is this project legally capable of being built, connected, energised, operated and monetised — within the claimed timeline and budget?

The key legal framework includes the Electricity and Gas Law no. 123/2012, ANRE Order 59/2013 on grid connection, ANRE Order 53/2024 and Order 79/2025 on capacity allocation, ANRE Order 105/2022 on grid connection contracts, ANRE Order 12/2015 on licences and establishment authorisations, Law 50/1991 on construction authorisation, environmental legislation, OUG 163/2022 as amended by OUG 59/2025, and EU law, especially Regulation 2019/943 and RED II / RED III.

2. The real object of DD: not the project, but the “legal energy asset”

In Romania, a renewable energy project is not one asset. It is a legal package made of several layers:

LayerWhat DD must verify | Why it matters
Corporate layerSPV ownership, share capital, debts, pledges, litigation, related-party contracts | Determines whether shares can be acquired cleanly
Land layerOwnership / superficies / lease / easements / agricultural status / cadastre | Without secured land, the project is not buildable
Permitting layerCU, environmental acts, avize, building permit, validity, amendments | Determines RTB status
Grid layerATR, solution study, connection contract, reinforcement works, guarantees, N/N-1, firm/non-firm capacity | Usually the most valuable and riskiest layer
Licensing layerANRE establishment authorisation, licence, certification, CfR | Determines ability to build and operate
Technical-regulatory layerRfG compliance, grid code, telemetry, SCADA, protection, storage integration | Determines energisation and grid acceptance
Commercial layerPPA, CfD, balancing, PRE/BRP, aggregation, GO, route-to-market | Determines revenue bankability
Financing layerState aid, PNRR, Modernisation Fund, securities, change of control consents | Determines whether acquisition triggers repayment or consent
Litigation/public law layerChallenges to permits, local opposition, administrative claims, environmental disputes | Determines timing and cancellation risk

A seller may say “the project is RTB”. In Romania, the DD answer should be more granular:

Permitting RTB — building permit exists. Grid RTB — ATR and grid connection agreement are valid, enforceable and financeable. Land RTB — all land and cable route rights are secured and opposable. ANRE RTB — establishment authorisation exists or is realistically obtainable. Commercial RTB — the project can reach COD and sell energy without a post-COD regulatory gap.

4. Core legal DD modules

A. Corporate and transaction DD

The first layer is classical M&A DD, but with energy-specific consequences.

You verify:

shareholders and UBOs
share transfers, pre-emption rights, drag/tag rights
shareholder loans and intra-group debt
pledges over shares, bank accounts, land rights or receivables
insolvency risk
litigation
tax liabilities
employees or consultants
exclusivity / brokerage / finder arrangements
hidden obligations toward developers, land aggregators, local intermediaries or grid consultants.

Real Romanian case: Many project SPVs are clean on paper but carry developer-side obligations in side agreements: success fees, land aggregation fees, local consultant success fees, grid-consultant arrangements, or obligations to reimburse development costs. A buyer should not only ask for the SPA and corporate documents; it should ask for all contracts entered into since incorporation, including “minor” service agreements.

DD conclusion: The issue is rarely whether the SPV exists. The issue is whether the SPV is clean enough to be acquired without inheriting hidden development economics.

B. Land DD

For PV and BESS, land DD is often the second most important workstream after grid.

You verify:

ownership chain
cadastre and land book registration
encumbrances, mortgages, interdictions, usufructs, easements
leases, superficies, option agreements, promises to sell
term of land rights versus project life
right to build, operate, cable, access, fence, maintain and decommission
co-ownership and spousal consent
agricultural classification
extravilan / intravilan status
land category and fertility class
archaeological, forestry, protected areas, military or aviation restrictions
access roads
cable route rights
substation land rights.
Real case 1: land secured for panels, but not for cable route

5. Project-stage DD: what matters at each stage

6. Red flag matrix

Red flagSeverity | Why
ATR expired or close to expiryCritical | Project may lose grid value
ATR not matching actual project capacity/layoutCritical | Re-approval may be required
GCA not signedHigh | Grid right not fully contractualised
Reinforcements required with uncertain dateHigh | COD and financing affected
Land secured only for PV plot, not cable routeCritical | Project may be unbuildable
Agricultural extravilan over 50 ha without clear legal routeCritical | Building permit risk
Building permit excludes BESS / station / lineHigh | Not fully RTB
Environmental act does not cover current designHigh | Revision / EIA risk
ANRE establishment authorisation missingHigh | 2026 guarantee and timing risk
No clear route-to-marketMedium/High | Revenue not bankable
PPA with weak offtakerMedium/High | Financing risk
State aid without change-of-control analysisCritical | Clawback risk
FDI clearance not assessedHigh | Closing illegality / fines risk
Seller refuses to disclose solution studyCritical | Grid economics unknown
“Zero reinforcement” not in ATR/GCAHigh | Marketing risk
BESS shown in teaser onlyHigh | Valuation overstatement

7. What a proper Romanian renewable DD report should conclude

A good DD should not simply say “documents reviewed, no major issues.” It should classify the project as one of these:

ClassificationMeaning
Bankable RTBLand, permits, grid, ANRE path and route-to-market are aligned
Legal RTB but not bankableBuilding permit exists, but grid/revenue/financing risk remains
Grid-secured but not permit-readyATR/GCA good, but permits not mature
Permit-ready but grid-weakBuilding permit exists, but ATR/GCA weak or constrained
Development assetMaterial missing permits or grid rights
Speculative assetMain value depends on future allocation / new ATR / uncertain capacity

This classification is more useful than the generic “RTB / non-RTB” label.

8. SPA protections buyers should request

For Romanian renewable acquisitions, the SPA should include:

Conditions precedent

valid ATR
valid GCA
proof of guarantee constitution
valid land rights
valid building permit
environmental act final and not challenged
ANRE establishment authorisation
FDI clearance
merger clearance if applicable
state aid consent if applicable
no litigation affecting permits
grid route rights secured.
Warranties
no undisclosed side agreements
no pending claims
no permit challenge
no breach of land agreements
no hidden grid conditions
no unpaid grid tariffs
no unauthorised works
no change in project design requiring permit revision
no state aid breach
no broker/finder claims except disclosed.
Indemnities
title defects
permit cancellation
state aid clawback
tax liabilities
undisclosed debt
environmental contamination
land restitution claims
invalid grid rights
undisclosed interconnection cost.
Price mechanisms
fixed price only for true RTB
staged payments for development assets
COD holdback
grid cost adjustment
capacity reduction adjustment
curtailment / N-1 adjustment
long-stop termination if CPs not met.

10. Practical conclusion

In Romania, legal due diligence for renewable energy projects in 2026 is no longer a document-counting exercise. It is a bankability audit.

The strongest projects are not simply those with an ATR or even a building permit. The strongest projects are those where the following five layers are aligned:

land — secured, registered, buildable, route included
grid — valid ATR, signed GCA, manageable costs, no fatal reinforcements
permits — environmental, urbanism and construction documents match the real project
ANRE — establishment authorisation/licence path is clear
revenue — PPA/CfD/merchant/BESS route-to-market is legally executable.

The biggest Romanian DD mistake is to overvalue “paper MW”. The real value is in MW that can survive legal scrutiny, connect to the grid, reach COD and produce bankable revenue.

Related reading and services

This article is part of the Romanian energy law content cluster. For the commercial route into a mandate, start with Energy Law in Romania and the Renewable Energy Legal Services page.

How Grigorescu Partners can help

Grigorescu Partners assists investors, developers, lenders and project owners with Romanian renewable energy projects, including legal due diligence, grid connection review, ANRE licensing, PPAs, BESS structuring, EPC and O&M contracts, project acquisitions and transaction execution.

If you are assessing a Romanian renewable energy project, the useful question is not only whether the project has documents. The useful question is whether those documents work together as a buildable, financeable and monetisable energy asset.