Short answer for investors

Legal guide to Romanian renewable energy EPC contracts for investors and developers, covering scope, delay, performance, BESS, security, direct agreements and bankability.

Why this matters in practice

A Romanian renewable EPC contract is the legal bridge between a permitted project and an operating asset. It should align scope, price, delay, performance, grid, ANRE, BESS, PPA/CfD and lender requirements.

Executive answer

A Romanian renewable EPC contract is the legal bridge between a permitted project and an operating asset. It should align scope, price, delay, performance, grid, ANRE, BESS, PPA/CfD and lender requirements.

Investor reading map

First questionDoes the EPC scope deliver the revenue-generating asset, not only construction works?
Second questionAre time, price and performance risks backed by meaningful remedies?
Third questionWill lenders accept the EPC structure for project finance?

1. Executive summary

An EPC contract — Engineering, Procurement and Construction — is the main construction contract under which a contractor typically undertakes to design, procure, construct, test, commission and hand over a renewable energy project. In Romania, EPC contracts are now central for:

utility-scale solar projects
co-located PV + BESS projects
standalone BESS projects
wind farm upgrades and battery retrofits
grid connection works
transformer stations
high-voltage evacuation lines
SCADA and dispatch integration

project-financed renewable assets.

A bankable EPC contract should answer five core questions: QuestionWhy it mattersWho is responsible for design?Design errors can delay permits, grid approval and performanceWho procures equipment?Modules, inverters, batteries, transformers and HV equipment drive cost and delay riskWho builds and integrates the project?Interface risk is critical in PV+BESS and grid worksWho bears delay risk?COD delay can trigger PPA, CfD, financing and grid consequencesWho guarantees performance?Underperformance directly affects revenue and valuation In Romania, the legal risk is rarely only “construction”. The real risk is interface: between EPC, permits, ATR, grid connection agreement, ANRE authorisation, equipment warranties, PPA/CfD deadlines, financing conditions and commissioning.

2. Why EPC contracts matter in Romania in 2026

Romania is no longer only a development pipeline market. Real construction is happening. Several public examples show the direction:

Simtel and HEPA Energy signed a contract of approximately RON 217 million for the design, construction and commissioning of a hybrid project in Sebeș, Alba County, consisting of around 68 MWp PV and 180 MWh BESS, with a 12-month implementation period and turnkey delivery.

Verbund Wind Power Romania selected Prime Batteries Technology and Enevo Group for the full EPC scope of a 48 MW / 76 MWh BESS at the Alpha Wind Nord wind farm in Tulcea County, including design, equipment supply, system integration, installation, commissioning and handover, with construction planned to start in February 2026 and commissioning targeted for September 2026.

Electrica signed an EPC contract for a 70 MWh standalone BESS project in Fântânele, Mureș County, with an estimated investment of EUR 16.5 million and completion targeted in 2026.

Allview Energy completed a 46 MWp solar plant in Țăndărei, Ialomița County under a full EPC contract, including design, equipment supply, execution, system integration, testing and technical documentation; the works also included a 35/110 kV station, underground high-voltage power line and integrated SCADA system.

3. What is an EPC contract?

An EPC contract is a construction contract where one contractor, or a consortium of contractors, takes responsibility for:

Engineering — design, technical studies, execution design, grid integration, technical documentation
Procurement — purchase and delivery of equipment, modules, inverters, batteries, transformers, switchgear, cables, SCADA, structures and other components
project-financed solar parks
PV+BESS projects
standalone BESS projects
projects with international lenders

projects where sponsor wants single-point responsibility.

Main advantage:

One contractor is responsible for delivering the complete project.

Main risk:

Contractor prices more risk, and the employer must define scope very precisely.

4.2 Split EPC

In a split EPC structure, different contractors handle different scopes. For example:

one contractor supplies PV modules
another supplies inverters
another performs civil works
another builds the transformer station
another builds the grid connection line
another integrates SCADA
another supplies batteries

another provides EMS / BMS.

This can reduce cost but increases interface risk. In Romania, split EPC can be tempting because of cost pressure, but it must be managed carefully. If the project is delayed, each contractor may blame another. Real risk: The battery supplier says the delay is caused by grid works. The grid contractor says SCADA data was late. The civil contractor says transformer foundations were redesigned. The owner is left managing the gap.

5. Key legal framework in Romania

5.1 Construction authorisation

Romanian construction works are generally governed by Law 50/1991. The law provides that civil, industrial, agricultural and other construction works may be carried out only in compliance with the building permit issued under the law and with design and construction regulations. For renewable energy projects, this means the EPC contractor must build strictly within the authorised project. If the EPC contractor changes the layout, transformer location, cable route, BESS configuration or technical design without proper permit analysis, the project may become non-compliant.

5.2 ANRE licensing and authorisation

The current ANRE licensing and authorisation framework is based on ANRE Order 6/2025, as amended by Order 26/2025. ANRE’s official page confirms that electricity-sector licensing and authorisation activities are carried out under this regulation. For EPC contracts, this matters because construction and commissioning must be aligned with:

ANRE establishment authorisation
ATR
grid connection agreement
technical conditions
commissioning and testing requirements

operating licence requirements.

The EPC contractor should not only build the physical plant. It should also deliver the documentation needed for commissioning, grid acceptance, ANRE licensing and COD.

5.3 Grid connection

The EPC scope must be consistent with the ATR and grid connection agreement. This includes:

connection point
delimitation point
connection installation
transformer station
MV/HV equipment
grid reinforcements
SCADA
metering

6. EPC and the Romanian project lifecycle

A renewable EPC contract should not be signed in isolation. It must be aligned with the project lifecycle. Stage 1 — Pre-EPC readiness Before signing the EPC contract, the owner should confirm:

land rights are secured
building permit is valid
environmental act covers the actual project
ATR is valid
grid connection agreement is signed or clearly pending
ANRE establishment authorisation is issued or obtainable
technical design is mature
soil and geotechnical studies are sufficient
cable route is secured
procurement assumptions are realistic

financing and CPs are aligned.

If this is not done, the EPC contract may become the place where all development gaps explode.

Stage 2 — Notice to proceed The EPC contract should distinguish between:

signing date
limited notice to proceed
full notice to proceed
financial close
site handover
commencement date
long-stop date

scheduled COD.

This distinction is important for Romanian projects because financing, land, grid and authorisation conditions may not all be ready on the same day. A contractor should not be fully liable for delay if the owner has not delivered permits, land access or grid interface conditions. At the same time, the owner should not accept an EPC contract where the contractor can delay mobilisation indefinitely.

Stage 3 — Construction During construction, the EPC contract must regulate:

site access
health and safety
environmental compliance
subcontractors
design approvals

7. Scope of work: the most important part of the EPC contract

The most common EPC mistake is an unclear scope. The EPC contract should define exactly what the contractor must deliver. For a solar PV project, scope should include:

detailed design
procurement of modules, inverters, structures, transformers, cables, switchgear
civil works
piling / foundations
mounting structures
DC and AC electrical works
MV/HV works
transformer station
internal roads
fencing and security
drainage
SCADA
metering
grid connection interface
testing and commissioning

documentation and handover.

For a BESS project, scope should include:

battery cells/modules/racks/containers or hall
PCS/inverters
EMS/BMS
HVAC
fire detection and suppression
transformers
MV/HV equipment
civil platform
safety systems
SCADA integration
grid compliance
testing
performance guarantees
degradation model

OEM documentation.

For a PV+BESS project, scope must also define the integration between PV and battery:

AC-coupled or DC-coupled
PV-only charging or grid charging
EMS priority logic
clipping recovery
PPA shaping
metering split
GO treatment

dispatch and optimisation interface.

If the contract does not clearly define the scope, the parties will later dispute whether an item was included in the EPC price.

8. Grid works and interface risk

In Romania, grid works are often the most sensitive EPC interface. The EPC may include:

internal collection network
transformer station
step-up transformer
MV/HV substation
underground cable
overhead line
SCADA
telecom
protection systems
connection works

testing with grid operator.

But some works may remain under the grid operator or separate contractors. The contract must define:

which works are EPC contractor’s scope
which works are owner’s scope
which works are grid operator’s scope
who coordinates with Transelectrica or DSO
who prepares technical documentation
who attends grid operator meetings
who bears delay caused by grid operator
who bears delay caused by missing documentation

who pays additional grid requirements.

Real Romanian issue: A project is delayed because the substation, SCADA or protection relay integration is not ready. The PV field may be complete, but the project cannot energise. In EPC drafting, “mechanical completion” should not be confused with “commercial operation”.

9. Price structure

EPC pricing can be structured in several ways.

9.1 Lump-sum turnkey

The contractor delivers the project for a fixed price. This is preferred by lenders because it reduces cost overrun risk. But the owner must ensure that:

scope is complete
exclusions are narrow
change order rules are strict
assumptions are disclosed
taxes, customs and transport are allocated
exchange-rate risk is addressed

equipment price escalation is addressed.

9.2 Unit price

Used where quantities may vary, such as cabling, civil works or trenching. This can be useful, but it reduces price certainty.

9.3 Cost-plus

Usually less bankable unless used for early works or limited pre-NTP activities.

9.4 Hybrid

Common in practice: fixed price for main plant, unit rates for variable works, provisional sums for grid-related or civil uncertainties. For Romanian renewable projects, a pure fixed-price EPC can be risky if the project has insufficient geotechnical data, unclear cable route or unresolved grid works.

10. Delay risk and liquidated damages

Delay is one of the most important EPC risks. A delay in Romania may affect:

PPA start date
CfD COD deadline
grid connection milestones
ANRE establishment authorisation validity
financing long-stop dates
equipment warranties
state aid deadlines
SPA deferred payments
tax assumptions

revenue model.

The EPC contract should include:

scheduled completion date
intermediate milestones
delay liquidated damages
cap on delay LDs
exclusive remedy or not
extensions of time
concurrent delay rules
force majeure
owner delay
grid operator delay
delay caused by authorities

acceleration rights.

Real case: Scatec’s Romanian solar portfolio benefits from a 15-year CfD for approximately 70% of estimated production. For CfD-backed projects, construction delay is not only a contractor-owner issue; it can affect support eligibility and revenue visibility. For CfD projects, EPC long-stop dates must be aligned with CfD deadlines.

11. Performance guarantees

Performance is as important as time. For PV projects, EPC performance guarantees may include:

installed capacity
performance ratio
availability
output test
grid compliance
SCADA functionality
degradation baseline

defect correction.

For BESS projects, guarantees may include:

usable energy capacity
charge/discharge power
round-trip efficiency
availability
response time
degradation
auxiliary consumption
EMS functionality
grid service readiness

safety system performance.

Performance liquidated damages should apply if the project fails performance tests. The contract must clearly state:

test procedure
weather correction
measurement period
reference standards
cure rights
retesting
LD calculation
rejection threshold

termination rights if minimum performance is not met.

For BESS, the EPC contract should be tightly connected to the OEM warranties. Otherwise, the EPC contractor may promise performance that the battery supplier does not support.

13. BESS-specific EPC issues

BESS EPC is more complex than PV EPC. A strong BESS EPC should cover: Battery degradation The contract must define:

initial usable capacity
annual degradation
cycle limits
depth of discharge
operating temperature
warranty assumptions
augmentation obligation

capacity maintenance.

Safety The contract must cover:

fire detection
suppression or containment
thermal runaway
emergency shutdown
firefighting access
firewater management
safety certification

emergency response plan.

Software and control The contract must cover:

EMS
BMS
SCADA
cybersecurity
remote monitoring
software licences
updates
data ownership

optimiser interface.

Revenue alignment If the financial model assumes aFRR, mFRR, arbitrage or PPA shaping, the EPC technical requirements must support those use cases. A BESS built only for energy shifting may not automatically qualify for balancing services.

14. PV+BESS EPC issues

PV+BESS contracts require an integrated approach. The contractor must deliver not just two assets, but one coordinated system. Key questions:

Is BESS AC-coupled or DC-coupled?

Can the battery charge from the grid?

Can it charge only from PV?

Can PV and BESS discharge simultaneously?

What is the export limit under the ATR?

Who controls dispatch logic?

How is clipping recovered?

How is BESS availability tested?

How are GOs treated for stored energy?

How is metering structured?

Does the BESS support the PPA product?

Simtel’s Sebeș contract is a useful public example because it expressly covers design, construction and commissioning of a hybrid PV+BESS plant of approximately 68 MWp plus 180 MWh storage, with turnkey delivery. Hybrid EPC requires more than adding a battery to a solar EPC form.

16. Interface with financing

For project-financed assets, lenders will expect the EPC contract to be bankable. Typical lender requirements include:

fixed price or controlled price risk
certain date for completion
delay LDs
performance LDs
appropriate liability cap
parent company guarantee
performance bond
advance payment bond
warranty bond
direct agreement
assignment rights
step-in rights
restrictions on termination
lender cure periods
insurance obligations

clear governing law and dispute resolution.

The EPC contractor must be financially strong enough to stand behind its obligations. If the EPC contractor is a thin SPV, the owner should request parent company support.

17. Interface with PPAs and CfDs

The EPC contract must be aligned with the project’s revenue contracts. PPA interface If the project has a PPA, the EPC must align with:

target COD
long-stop COD
contracted capacity
delivery profile
performance obligations
availability assumptions
curtailment provisions
GOs

testing and acceptance.

If the EPC is delayed, the project may lose PPA revenue or face termination. CfD interface If the project benefits from a CfD, the EPC must align with:

CfD milestone deadlines
financial close
COD deadline
performance requirements
state aid conditions
reporting obligations

grid connection deadlines.

For Scatec’s 190 MW Romanian solar portfolio, the projects are supported by a 15-year CfD covering around 70% of estimated production, showing how construction, financing and revenue support must be integrated.

18. Change orders

Change orders are a major source of EPC disputes. The contract should define:

what qualifies as a change
who may request it
what happens if law changes
what happens if grid operator changes requirements
how price is adjusted
how time is adjusted
whether contractor must proceed pending agreement
what records are required

whether oral instructions are valid.

In Romania, changes often arise from:

grid operator requests
permit amendments
environmental authority conditions
soil surprises
land access issues
cable route changes
equipment substitution
design optimisation

lender technical advisor comments.

A good EPC contract should not prevent all change. It should make change manageable.

20. Liability caps

A bankable EPC contract must define liability caps carefully. Common caps include:

overall liability cap
delay LD cap
performance LD cap
uncapped liability for fraud, wilful misconduct, IP infringement, confidentiality, death/personal injury, environmental breaches or gross negligence
separate cap for warranty obligations

exclusion of indirect loss.

The owner should avoid a structure where the liability cap is so low that delay LDs and performance LDs exhaust the contractor’s exposure before major defects are discovered. For BESS, separate caps may be needed for safety, degradation and capacity warranties.

21. Security package

A renewable EPC contract should normally include:

performance bond
advance payment bond
parent company guarantee
retention
warranty bond
insurance
assignment of OEM warranties

subcontractor collateral warranties, where relevant.

For lenders, these instruments are crucial. For owners, they are the difference between having a contractual claim and having real recovery.

22. Insurance

The EPC contract should require appropriate insurance, such as:

construction all risks
third-party liability
employer’s liability
professional indemnity for design
cargo / marine transport insurance
delay in start-up insurance, if available
environmental liability
cyber insurance, where relevant

BESS fire and thermal runaway risk coverage.

For BESS projects, insurance availability and exclusions should be reviewed early. Some insurers may impose specific technical and safety requirements.

25. Real Romanian EPC risk cases

Below are the recurring Romanian EPC risk scenarios investors should understand. Case 1 — EPC signed before project is truly RTB The owner signs EPC before land, permits, GCA or ANRE authorisation are fully aligned. Contractor later claims extension of time and additional cost. Solution: EPC signing can happen early, but full NTP should be conditional on project readiness.

Case 2 — PV-only EPC used for PV+BESS The contract is adapted from a solar template and does not properly address battery degradation, fire safety, EMS, metering or revenue use cases. Solution: Use BESS-specific technical schedules and performance tests.

Case 3 — Grid works outside EPC scope The plant is complete but cannot energise because station, cable, SCADA or protection works are delayed. Solution: Define grid interface, responsibility matrix and coordination obligations.

Case 4 — Owner-supplied equipment causes delay The owner procures modules or batteries directly. Delivery is late. Contractor claims extension of time. Solution: Allocate owner-supplied equipment risk clearly.

Case 5 — Performance test unclear The project is built, but the parties dispute whether performance ratio or battery capacity test was passed. Solution: Define test methodology, correction factors and retesting procedure.

Case 6 — Permit mismatch Contractor builds according to optimised design, but the authorised design was different. Solution: Any design change must trigger legal permit review before implementation.

Case 7 — CfD or PPA deadline missed Construction delay causes the project to miss revenue support or offtake deadlines. Solution: Align EPC LDs with commercial exposure, or at least avoid a major uncovered gap.

Case 8 — EPC contractor is not financially strong enough The contract has good wording but the contractor has limited balance sheet. Solution: Require parent guarantee, bond, retention and bankable security.

26. EPC due diligence checklist

Before signing or acquiring a project with an EPC contract, review: Contract structure

Full EPC, split EPC, EPCM or supply/install?

Is responsibility single-point or fragmented?

Is the contractor financially credible?

Is there parent support?

Scope

Is scope complete?

Are exclusions limited?

Are grid works included?

Are SCADA and metering included?

Are BESS/fire systems included?

Are testing and documentation included?

Price

Lump sum or variable?

What assumptions apply?

What is excluded?

What triggers change orders?

Are taxes, customs and FX addressed?

Time

What is commencement date?

What is scheduled COD?

Are milestones clear?

Are delay LDs sufficient?

Are extension of time rules fair?

Is grid delay allocated?

Performance

What tests apply?

What performance guarantees exist?

Are LDs sufficient?

Is rejection/termination possible?

Are OEM warranties aligned?

Permits and grid

Who handles permit amendments?

Who coordinates with grid operator?

Who prepares ANRE/grid documentation?

Who bears risk of grid operator requirements?

Is GCA scope reflected?

BESS

Are battery warranties included?

Is degradation covered?

Is fire safety covered?

Is EMS/BMS included?

Is revenue functionality tested?

Security

Performance bond?

Advance payment bond?

Warranty bond?

Parent company guarantee?

Retention?

Insurance?

Financing

Direct agreement?

Assignment rights?

Step-in?

Lender cure periods?

Termination restrictions?

27. Drafting recommendations

A strong Romanian renewable EPC contract should include:

detailed employer’s requirements
clear priority of documents
complete technical schedules
grid interface matrix
permitting responsibility matrix
milestone schedule
delay LDs
performance LDs
robust testing regime
change order procedure
equipment approval list
OEM warranty assignment
BESS degradation and safety clauses, where applicable
HSE and ESG obligations
insurance requirements
security package
lender direct agreement
dispute escalation
governing law and arbitration/court forum

handover documentation list.

The most important drafting point is this:

The EPC contract must not only describe what will be built. It must describe what must be delivered for the project to generate revenue.

28. Investor conclusion

EPC contracts are becoming one of the most important legal documents in Romanian renewable energy projects. As Romania moves from development pipeline to construction delivery, investors and lenders will increasingly focus on whether projects can be built on time, on budget and in full compliance with grid, permitting and ANRE requirements. A weak EPC contract can destroy the value of a strong project. A strong EPC contract can protect the value created by land, permits, ATR, GCA, financing and route-to-market. For solar projects, the key risks are scope, grid connection, performance ratio and COD delay. For BESS projects, the key risks are safety, degradation, EMS/BMS, availability and revenue functionality. For PV+BESS projects, the key risk is integration. For CfD-backed projects, the key risk is missing support deadlines. For project-financed assets, the key risk is whether the EPC is bankable. In Romania, renewable energy EPC is no longer just construction. It is the legal bridge between a permitted project and an operating asset. And in 2026, that bridge must be drafted very carefully.

Related reading and services

This article is part of the Romanian energy law content cluster. For the commercial route into a mandate, start with Energy Law in Romania and the Renewable Energy Legal Services page.

How Grigorescu Partners can help

Grigorescu Partners assists investors, developers, lenders and project owners with Romanian renewable energy projects, including legal due diligence, grid connection review, ANRE licensing, PPAs, EPC and O&M contracts, project acquisitions, project finance support and transaction execution.

If you are assessing a Romanian renewable energy project, the useful question is not only whether the project has documents. The useful question is whether those documents work together as a buildable, financeable and monetisable energy asset.