Short answer for investors

Lender-focused legal due diligence guide for Romanian renewable energy projects, covering land, grid, ANRE, EPC, revenue, security, direct agreements and bankability.

Why this matters in practice

Lender due diligence for Romanian renewable energy projects is a bankability audit. It tests whether land, grid, permits, ANRE approvals, EPC, revenue contracts, security and direct agreements support debt service.

Executive answer

Lender due diligence for Romanian renewable energy projects is a bankability audit. It tests whether land, grid, permits, ANRE approvals, EPC, revenue contracts, security and direct agreements support debt service under prudent assumptions.

Investor reading map

First questionCan the project reach COD without a legal or grid blocker?
Second questionCan the revenue model support debt service under downside assumptions?
Third questionCan the lender preserve and enforce project value after default?

1. Executive summary

Lender due diligence for renewable energy projects in Romania is more demanding than buyer-side legal due diligence.

A buyer may accept some development risk if the price is attractive. A lender usually cannot. The lender needs a project that can support repayment of debt within a predictable legal, technical and commercial framework.

A bankable Romanian renewable project should normally pass eight core tests:

Lender testKey question
Project companyIs the borrower clean, solvent, properly authorised and ring-fenced?
LandAre land rights enforceable for the full debt tenor and capable of being secured?
PermitsAre environmental, construction and sector permits valid, final and aligned with the project?
GridAre ATR, grid connection agreement, connection tariff, guarantees and reinforcement works bankable?
ANREAre establishment authorisation and operating licence path clear?
ConstructionIs the EPC contract fixed-price, date-certain and performance-backed?
RevenueAre CfD, PPA, merchant, BESS or balancing revenues legally robust and financeable?
SecurityCan the lender take and enforce effective security over shares, accounts, receivables, land rights, project contracts and insurance proceeds?

In 2026, the biggest lender-side risks in Romania are:

2. Why lender DD is becoming more important in Romania

Publicly announced transactions show that lenders are increasingly willing to finance Romanian renewable energy projects, but only where the structure is robust.

In March 2026, Enery reached financial close on a EUR 460 million syndicated green project financing for the Ogrezeni hybrid project in Giurgiu County, combining 761 MWp / 534 MW AC solar PV with more than 1 GWh of battery storage. The lender syndicate included UniCredit, Intesa Sanpaolo Group, ING, Banca Transilvania, National Bank of Greece (Cyprus), Exim Banca Românească and Alpha Bank.

In February 2026, Scatec reached financial close for its 190 MW Dobrun & Sadova solar portfolio in Romania. The projects are supported by a 15-year CfD with OPCOM covering approximately 70% of estimated production, with the remainder sold on the Romanian wholesale electricity market. BCR reported that the total financing package was approximately EUR 121 million, provided by BCR, the European Investment Bank and the European Bank for Reconstruction and Development, with BCR providing EUR 42.5 million through long-term financing, VAT and construction-phase credit facilities.

Also in February 2026, BCR and Erste Group provided EUR 58.5 million financing for Greenvolt Power’s 49.8 MW onshore wind project in Săcele, Constanța County, with construction expected to be completed in Q2 2026.

3. Lender DD is different from buyer DD

Buyer due diligence asks: “What am I buying?”

Lender due diligence asks: “What can I rely on if the project underperforms?”

That creates a different mindset.

A buyer may accept that the project will obtain an ANRE establishment authorisation after closing. A lender may require it as a condition precedent to first drawdown.

A buyer may accept a PPA with some open imbalance issues. A lender will ask whether the PPA revenue can support debt service after imbalance costs, curtailment and negative-price exposure.

A buyer may accept a project with partial route rights. A lender will ask whether the cable route is legally secured for construction, operation, enforcement and step-in.

A buyer may value BESS upside. A lender will ask whether BESS revenue is contracted, technically qualified, licensed and realistically available.

This is why lender DD must be stricter, more conservative and more cash-flow oriented.

4. The Romanian lender DD framework

For a Romanian renewable energy project, lender due diligence usually covers:

corporate and borrower due diligence
title and land due diligence
permitting and environmental due diligence
grid connection due diligence
ANRE authorisation and licensing due diligence
construction / EPC due diligence
O&M and asset management due diligence
revenue contract due diligence
BESS / storage revenue due diligence, where applicable
insurance due diligence
tax and accounting due diligence
FDI, merger control and regulatory approvals
state aid / CfD / grant compliance
security package and enforceability
direct agreements and step-in rights.

The legal report should not only list documents. It should classify risks by impact on construction, COD, revenue, debt service and enforcement.

5. Corporate and borrower due diligence

The lender’s first question is whether the borrower is a clean, financeable SPV.

A Romanian project SPV should normally be ring-fenced. It should not carry unrelated debt, operating liabilities, historic disputes or hidden development obligations.

Lender DD should check:

incorporation documents
shareholders and UBOs
share capital
shareholder loans
intra-group debt
existing pledges
related-party contracts
accounting records
tax liabilities
litigation
insolvency risk
employment liabilities
hidden broker or development success fees
board approvals
capacity to enter into finance documents
authority to grant security.

The lender will also care about change-of-control and transfer restrictions. If the project was acquired from a developer, the lender should confirm that no undisclosed earn-out, success fee or vendor lien affects the borrower.

Real Romanian risk

Many renewable SPVs are clean in the trade registry, but not necessarily clean economically. Side letters, development agreements, land aggregator success fees or consultant mandates may survive after closing. For a lender, this is not just an M&A issue. It is leakage risk.

6. Sponsor due diligence

In project finance, sponsors matter.

The Enery Ogrezeni financing is a useful public example: Enery itself described the transaction as reflecting strong lender appetite for well-structured hybrid renewable projects and strong sponsors.

Lenders will usually assess:

sponsor track record
sponsor financial strength
equity funding capacity
prior project delivery
technical capability
experience in Romania
related-party EPC/O&M arrangements
shareholder support obligations
completion support
cost overrun support.

Where the project is still under construction, lenders may require sponsor support until COD. This can include equity commitment letters, cost overrun support, completion undertakings or subordinated shareholder loans.

Practical point

A strong sponsor can make a complex Romanian project financeable. A weak sponsor can make even a good project difficult to finance.

7. Land due diligence from a lender perspective

Land due diligence is stricter for lenders because land rights must support the full debt tenor and enforcement scenario.

The lender should verify:

ownership / superficies / lease rights
duration of land rights
renewal rights
registration in the land book
mortgages and encumbrances
co-ownership issues
access rights
cable route rights
substation land
rights for maintenance and replacement
decommissioning obligations
agricultural land restrictions
removal from agricultural circuit
compatibility with building permit
ability to mortgage or assign land rights.

For solar and BESS projects, the lender should never review only the main project land. It must also review:

internal roads
public access road
cable route
transformer station
switching station
connection corridor
temporary construction areas
heavy transport access
fire safety perimeter, for BESS.
Real Romanian risk

A project may have secured the PV land but not the cable route to the 110 kV or 400 kV station. From a lender’s perspective, that is a major bankability issue. A project that cannot evacuate electricity cannot service debt.

Lender requirement

Land rights should be capable of being secured, assigned or stepped into. If the borrower defaults, the lender or replacement operator must be able to access, operate and transfer the project.

8. Permitting and environmental due diligence

A lender will require permits that are valid, final, enforceable and aligned with the project actually being financed.

The legal review should cover:

certificate of urbanism
environmental decision / agreement
building permit
grid-related permits
ISU / fire safety path, especially for BESS
agricultural circuit removal
avize required by the CU
permit validity and extension
commencement notices
compliance with authorised design
challenges or litigation
authority correspondence
amendment requirements.

For BESS, the European Commission’s 2026 approval of Romania’s EUR 150 million storage scheme confirms the policy importance of storage, but it also means lenders will pay close attention to storage-specific environmental, fire safety and state-aid conditions. The scheme supports at least 2,174 MWh of new standalone battery storage through direct grants financed by the Modernisation Fund, with beneficiaries selected through competitive tendering.

Real Romanian risk

A project may be financed as PV + BESS, but the environmental act and building permit may cover only PV. In that case, the lender should treat BESS revenue as unbankable until the BESS component is fully permitted.

Lender requirement

The financed project must match the permitted project. If the technical adviser’s design differs from the legal permits, the discrepancy must be cured before drawdown or treated as a condition subsequent with strong controls.

9. Grid connection due diligence

Grid due diligence is the heart of lender due diligence in Romania.

The relevant legal framework still starts from ANRE’s grid connection rules, including Order 59/2013 and subsequent amendments; ANRE’s archived English page identifies Order 59/2013 as the regulation on connection to public-interest electricity networks.

A lender will usually require:

valid ATR
solution study
signed grid connection agreement
connection tariff confirmation
payment schedule
proof of payments
financial guarantees
reinforcement works analysis
grid works responsibility matrix
energisation conditions
curtailment / limitation analysis
SCADA, protection and metering obligations
connection route land rights
no default under GCA
no pending challenge or termination risk.
ATR is not enough

A lender will rarely be comfortable with an ATR alone. The grid connection agreement is usually essential because it contractualises works, costs, deadlines and responsibilities.

Reinforcement risk

The lender must understand whether connection depends on:

specific reinforcement works
general upstream reinforcements
Transelectrica works
DSO works
third-party projects
new substation
line upgrades
protection and SCADA integration.

If the project can be built but not energised before grid works are completed, debt availability should be linked to grid milestones.

10. Capacity allocation and new grid guarantees

The Romanian capacity allocation framework is now central for projects of at least 5 MW.

Transelectrica’s procedure under ANRE Order 53/2024 governs annual auctions for grid capacity allocation for generation sites of at least 5 MW, including storage and combined consumption-generation points, with capacity available at 220/400 kV transmission level and 110 kV distribution level by network zones. ANRE later approved Order 79/2025, amending Order 53/2024 and preparing implementation from 1 January 2026.

This matters for lenders because allocation risk is not theoretical. If a project has not secured grid capacity, it may not be financeable.

The April 2026 ANRE reform direction is also critical. ANRE announced a package including a new guarantee for capacity allocation auction participation, an increase of the connection guarantee from 5% to 20% of the connection tariff, and an establishment-authorisation guarantee of EUR 30/kW installed.

Lender questions

The lender should ask:

Is the project grandfathered or subject to capacity allocation? Has capacity allocation been secured? Has the allocation contract been signed? Are payments due? Are guarantees constituted? Can guarantees be enforced? Are guarantees included in project cost? Are guarantee costs funded by equity or debt? What happens if capacity is reduced or lost? Practical conclusion

11. ANRE licensing due diligence

ANRE licensing is another lender-critical item.

ANRE’s official page states that electricity-sector licences and authorisations are granted under the regulation approved by ANRE Order 6/2025, published in the Official Gazette on 26 March 2025 and amended by Order 26/2025.

For renewable projects, lender DD should cover:

whether ANRE establishment authorisation is required
whether it has been issued
validity period
extension risk
whether storage is included
whether project phasing is included
consistency with ATR, building permit and environmental act
risk of suspension or withdrawal
operating licence path
production licence
storage licence
trader / supplier / aggregation rights if relevant.
BESS-specific issue

A BESS project may require more than a storage authorisation. If the revenue model includes trading, balancing, aggregation or portfolio optimisation, the lender must check whether the SPV or relevant market participant has the necessary rights and qualifications.

Lender requirement

For construction financing, establishment authorisation may be a condition precedent. For term conversion or COD, the operating licence and grid connection certificate should be conditions.

12. Construction and EPC due diligence

The EPC contract is one of the most important documents for lenders.

Public Romanian transactions show that EPC structure is central to financing. In the Scatec 190 MW solar portfolio, Defic Globe provides EPC services while Scatec provides O&M and asset management services. In the Enery Ogrezeni hybrid financing, the size and complexity of the 761 MWp solar plus 1 GWh BESS project make construction interface and completion risk central to lender analysis.

Lender EPC DD should check:

fixed price or variable price
full turnkey or split EPC
scope completeness
grid works interface
BESS integration scope
employer’s requirements
technical schedules
milestones
scheduled COD
delay liquidated damages
performance liquidated damages
liability caps
parent company guarantee
performance bond
advance payment bond
warranty bond
force majeure
change orders
testing and commissioning
handover documentation
direct agreement with lender.
Common lender concern

A project may be “ready to build” legally but not “ready to finance” if the EPC contract is weak. A lender will want to see date certainty, price certainty and performance certainty.

BESS EPC

For BESS, lender DD must also review:

battery warranties
degradation curve
availability guarantee
usable capacity test
round-trip efficiency
fire safety
EMS/BMS
SCADA integration
response time
augmentation obligations
OEM warranty assignment.

14. Revenue due diligence: CfD, PPA, merchant and BESS

Revenue DD is where lender analysis becomes most commercial.

Romania’s CfD scheme is highly relevant. The EBRD states that Romania’s two-way CfD scheme provides long-term revenue stability to developers and strengthens market integration of renewables. The second auction awarded 2,751 MW, bringing the first and second auction total to 4.2 GW, with solar PV bids as low as EUR 35/MWh.

For lenders, this means CfD-backed projects may be more bankable than purely merchant projects, but only if CfD compliance is robust.

14.1 CfD-backed projects

Lender DD should cover:

CfD contract
strike price
reference price
eligible production
COD deadline
performance security
termination
negative-price rules
change of control
state aid compliance
reporting
interaction with PPA or market access contract.

Scatec’s 190 MW project illustrates the lender logic: roughly 70% of estimated production is covered by a 15-year CfD, while the remaining production is sold on the wholesale market. This is the type of blended revenue structure lenders can model more clearly than fully merchant exposure.

14.2 PPA-backed projects

For PPAs, lenders should review:

tenor
price
volume
product type
as-produced versus fixed volume
imbalance allocation
curtailment
negative prices
offtaker credit
parent guarantee or letter of credit
direct agreement
assignment of receivables
termination payments
change in law.

15. Guarantees of origin and ESG revenue

Guarantees of origin can matter for PPAs and ESG reporting.

EY notes that Romania’s guarantees of origin regime is evolving from a traceability instrument toward a more operational market tool; ANRE obtained AIB observer status at the end of November 2025, Romania targets full AIB membership from 1 June 2026, and a fully functioning standardised GO market is targeted for 1 January 2027.

For lenders, GO revenue should be treated carefully.

Unless the project has a clear contractual right to monetise GOs, GO upside should usually remain outside the conservative base case.

For PPA-backed projects, the lender should check:

who owns GOs
whether GOs are bundled with energy
whether GO transfer is required
whether failure to transfer GOs is an event of default
whether GO revenue is pledged
whether GO revenue is included in the financial model.

16. State aid and grant due diligence

Romanian renewable projects may benefit from:

CfD
Modernisation Fund
PNRR
storage grants
investment aid
legacy green certificates
other public schemes.

The European Commission approved Romania’s EUR 3 billion CfD support scheme for onshore wind and solar PV in March 2024. The Commission also approved the 2026 EUR 150 million Romanian storage scheme for at least 2,174 MWh of new standalone BESS.

Lender DD should check:

eligibility
grant agreement
procurement rules
DNSH obligations
cumulation rules
change-of-control restrictions
security restrictions
assignment restrictions
COD deadlines
reporting obligations
clawback events
breach consequences.
Lender concern

State aid can improve economics but reduce flexibility. A lender must know whether enforcement, share pledge enforcement, project transfer or change of control could trigger clawback or consent requirements.

17. FDI, merger control and regulatory approvals

Renewable energy and grid infrastructure may fall within sensitive sectors for investment screening.

Romania’s FDI screening regime was amended by GEO 17/2026, applicable from 13 March 2026. The mandatory filing threshold increased to EUR 5 million, but sub-threshold investments may still be examined where national security concerns arise, and asset deals in sensitive sectors are expressly included.

The International Bar Association’s March 2026 summary also notes that the revised regime captures energy, infrastructure and strategic technologies, and introduces aggregation rules for related transactions carried out within one year.

For lenders, FDI matters in three ways:

acquisition financing may require FDI clearance before closing
security enforcement may transfer control to a foreign investor or security agent
asset deals or portfolio restructurings may trigger review.
Lender requirement

Finance documents should include conditions precedent, representations and covenants covering FDI and merger control compliance.

18. Insurance due diligence

Insurance is not a formality in renewable project finance.

The lender should review:

construction all risks
third-party liability
delay in start-up / advanced loss of profit, if available
cargo / marine transit
professional indemnity for design
operational all risks
business interruption
machinery breakdown
environmental liability
cyber insurance
BESS fire / thermal runaway coverage
lender loss payee clauses
notice of cancellation
waiver of subrogation
assignment of insurance proceeds.

For BESS, insurance availability can be affected by technology, safety design, separation distances, fire suppression and operating regime.

A project with weak BESS fire protection may face higher premiums, exclusions or lender objections.

19. Security package

A lender’s security package for a Romanian renewable project will usually include:

share pledge over borrower shares
bank account pledge
mortgage over land or superficies rights, where available
movable mortgage over equipment
pledge over receivables
assignment of project contracts
assignment of insurance proceeds
pledge over intra-group loans
security over GO revenues, where applicable
direct agreements with key counterparties
sponsor support documents
subordination agreements.

The enforceability of each security item must be checked under Romanian law.

Practical lender issue

If the project land is leased, the lender may not be able to take a classic mortgage over ownership. It may need security over contractual rights, superficies, receivables and step-in rights.

20. Direct agreements and step-in rights

Direct agreements are central to lender bankability.

They should be obtained from:

EPC contractor
O&M contractor
PPA offtaker
CfD counterparty, where possible / applicable
grid-related contractors
landowners, where critical
optimiser / route-to-market provider for BESS
key OEMs, where relevant.

Direct agreements typically provide:

notice of default
lender cure period
step-in rights
restrictions on termination
consent to assignment
acknowledgment of security
replacement operator rights.

Without direct agreements, a lender may have security on paper but limited ability to preserve project value after default.

21. Conditions precedent to first drawdown

A lender will typically require CPs such as:

constitutional documents
corporate approvals
financial model approval
permits
land rights
valid ATR
signed GCA
proof of grid payments and guarantees
ANRE establishment authorisation
EPC contract
O&M contract
insurance
technical adviser report
environmental and social report
tax report
legal DD report
security documents
direct agreements
sponsor equity funded or committed
FDI/merger/state aid approvals
no litigation
no material adverse change.

For construction financing, lenders may allow some items to be conditions subsequent, but only if they do not threaten COD, security or debt service.

24. Lender risk matrix

RiskLender concern | Typical mitigation
ATR without GCAConnection not fully contractualised | GCA as CP
Reinforcement worksCOD delay | Grid milestone CP / reserve
Capacity allocationLoss of grid capacity | Allocation contract and payment proof
20% connection guaranteeCapital blocked / enforcement risk | Funded guarantee and covenant
Missing ANRE authorisationConstruction/licensing gap | Establishment authorisation CP
Missing cable routeProject cannot connect | Route rights CP
Permit mismatchIllegal construction / delay | Permit matrix
EPC weak LDsUncovered delay exposure | Bankable LDs and security
BESS revenue speculativeDebt not supported by cash flow | Contracted revenue or conservative sizing
Weak PPARevenue risk | Credit support / direct agreement
CfD breachLoss of support | CfD compliance CP/covenants
State aid clawbackRepayment risk | State aid legal opinion
FDI clearanceClosing/enforcement delay | FDI CP and covenant
Insurance exclusionsUncovered casualty risk | Lender-approved insurance
Security gapsWeak enforcement | Full Romanian security package

25. Practical lender DD checklist

  • Project company Clean SPV?
  • No unrelated debt?
  • No hidden fees?
  • No litigation?
  • Shareholder loans subordinated?
  • Corporate approvals valid?
  • Land Full project land secured?
  • Cable route secured?
  • Rights registered?
  • Debt tenor covered?
  • Security possible?
  • Step-in possible?
  • Permits Environmental act valid?
  • Building permit valid?
  • BESS/fire safety covered?
  • No challenges?
  • No expiry risk?
  • Project design aligned?
  • Grid ATR valid?
  • GCA signed?
  • Connection tariff final?
  • Payments made?
  • Guarantees issued?
  • Reinforcements clear?
  • Curtailment understood?
  • Capacity allocation secured?
  • ANRE Establishment authorisation issued?
  • Licence path clear?
  • Storage included?
  • Extension risk?
  • No sanction/suspension risk?
  • Construction EPC fixed-price?
  • Date-certain?
  • Delay LDs?
  • Performance LDs?
  • Bonds?
  • Parent guarantee?
  • Direct agreement?
  • Interface risks covered?
  • Revenue CfD/PPA/merchant/BESS split?
  • Base case and downside case?
  • PPA credit support?
  • GO treatment?
  • Imbalance costs?
  • Curtailment?
  • Negative prices?
  • Security Shares?
  • Accounts?
  • Receivables?
  • Land/superficies?
  • Equipment?
  • Contracts?
  • Insurance?
  • Direct agreements?

26. Conclusion: lender DD is a bankability audit

In Romania, lender due diligence for renewable energy projects is not a legal formality.

It is a bankability audit.

The lender must determine whether the project can move from development to construction, from construction to COD, and from COD to stable debt service.

That requires a legal review of land, permits, grid, ANRE, EPC, O&M, revenue contracts, state aid, FDI and security. But it also requires a commercial understanding of how these documents interact.

A valid ATR is not enough. A signed PPA is not enough. A building permit is not enough. A BESS financial model is not enough.

For a lender, the project is bankable only when the legal structure supports the financial model.

In Romania’s 2026 renewable energy market, the strongest projects will be the ones that can prove not only that they exist on paper, but that they can connect, operate, generate revenue and repay debt.

That is the standard lender due diligence must apply.

Related reading and services

This article is part of the Romanian energy law content cluster. For the commercial route into a mandate, start with Energy Law in Romania and the Renewable Energy Legal Services page.

How Grigorescu Partners can help

Grigorescu Partners assists investors, developers, lenders and project owners with Romanian renewable energy projects, including legal due diligence, grid connection review, ANRE licensing, PPAs, EPC and O&M contracts, project acquisitions, project finance support and transaction execution.

If you are assessing a Romanian renewable energy project, the useful question is not only whether the project has documents. The useful question is whether those documents work together as a buildable, financeable and monetisable energy asset.