Short answer for investors

Legal guide to standalone BESS projects in Romania, covering land, permitting, fire safety, grid import/export, ANRE licensing, market participation and bankability.

Why this matters in practice

Standalone BESS projects in Romania are regulated electricity assets. Investors should test land rights, permitting, grid connection, ANRE authorisations, operating licences, revenue strategy and bankability before.

Executive answer

Standalone BESS projects in Romania are regulated electricity assets. Investors should test land rights, permitting, grid connection, ANRE authorisations, operating licences, revenue strategy and bankability before treating a project as financeable.

Standalone BESS is becoming one of the most important energy investment themes in Romania.

For years, storage was discussed mainly as an accessory to solar or wind. In 2026, that has changed. Standalone battery energy storage systems are now being developed as independent infrastructure assets, with their own land, ATR, grid connection, ANRE authorisation, operating licence, revenue model and financing logic.

The legal question is no longer:

“Can batteries be added to a renewable project?”

The real investor question is:

Can a standalone BESS project in Romania be permitted, connected, licensed, financed and monetised as an independent regulated electricity asset?

The answer is yes — but only if the project is structured correctly from the beginning.

Investor reading map

First questionIs the asset legally permitted to exist as a standalone storage project?
Second questionDoes the grid connection allow the commercial model that the investor is pricing?
Third questionAre ANRE licensing, market participation and financing assumptions aligned?

1. Executive summary

A standalone BESS project in Romania is not a normal real estate project, and it is not simply “equipment on land”.

It is a regulated electricity asset.

A bankable standalone BESS project should normally have:

LayerWhat must be checked
CorporateClean SPV, no hidden development obligations, no undisclosed grid or land claims
LandSecure land rights for BESS containers/building, transformer station, access road, cable route and safety perimeter
PermittingCertificate of urbanism, environmental decision/agreement, building permit, fire safety pathway, grid-related permits
GridATR, grid connection agreement, clear import/export capacity, connection tariff, guarantees, reinforcement risk
Capacity allocationWhether the project falls under the 2026 auction mechanism for ≥5 MW storage
ANREEstablishment authorisation if above threshold; standalone storage operating licence before commercial operation
TechnicalGrid code, SCADA, telemetry, metering, protection, dispatchability, safety certification
RevenueArbitrage, imbalance optimisation, balancing services, ancillary services, portfolio optimisation, capacity/flexibility support
State aidModernisation Fund / CISAF / grant conditions, if applicable
TransactionChange of control, asset transfer, FDI, financing, step-in rights, EPC and OEM bankability

The main point is this:

A standalone BESS project is valuable only if the battery can legally charge, discharge, connect, participate in markets and capture the revenue assumed in the financial model.

3. What is a standalone BESS project?

A standalone BESS is a battery energy storage project that is not merely an accessory to a specific solar or wind power plant.

It is independently connected to the grid and usually has its own:

land
grid connection solution
ATR
connection agreement
import and export capacity
metering
ANRE authorisation and licence
market participation structure
revenue stack.

This is different from a co-located BESS.

TypeLegal logic
Co-located BESSStorage added to or integrated with a PV/wind project, often at the same grid connection point
Standalone BESSIndependent storage installation, capable of charging from and discharging into the grid
Behind-the-meter BESSStorage located at a consumption site, used for self-consumption, peak shaving or flexibility
Hybrid clusterCombination of PV/wind plus standalone or co-located storage under a wider commercial strategy

RED III defines “co-located energy storage” as a storage installation combined with a renewable energy plant and connected at the same grid access point. This distinction is commercially important because a standalone BESS has a different permitting and revenue profile from a storage unit added to an existing renewable plant.

5. Permitting a standalone BESS project in Romania

A standalone BESS project usually follows a permitting path similar to an industrial energy facility, but with additional safety and grid-specific issues.

5.1 Land rights

The first question is whether the project company has the right land.

A standalone BESS usually needs land for:

battery containers or battery hall
power conversion systems
transformers
medium/high-voltage equipment
control building
firefighting water or fire protection infrastructure
internal roads
crane access
security perimeter
cable route
connection line
possible substation extension.

Legal DD should check:

ownership, superficies or lease rights
land book registration
mortgage or encumbrance
land use category
industrial compatibility
right to build energy/storage assets
access to public road
heavy transport access
servitudes for cable route
distance from neighbours and sensitive receptors
compatibility with fire safety and environmental requirements.

Real case: A BESS developer secures the plot for the containers, but not the cable route to the 110 kV station. The project is not bankable. For BESS, connection route is not a secondary issue. It is part of the asset.

5.2 Certificate of urbanism

The certificate of urbanism is the starting point for construction permitting.

For BESS, the CU should be reviewed carefully to see whether the local authority understands the project as:

energy storage facility
industrial / utility facility
electricity infrastructure
temporary containers
permanent construction
transformer station plus storage units.

The classification matters because it affects:

required endorsements
environmental procedure
fire safety pathway
building permit documentation
compatibility with zoning.

Real case: A developer describes the BESS as “containers”. The local authority treats it as a simple container placement. Later, the environmental authority and ISU treat it as an industrial energy storage facility. The permitting path becomes inconsistent.

5.3 Environmental permitting

Environmental review is critical for BESS, even though batteries do not generate emissions like thermal plants.

6. ANRE licensing for standalone BESS

Standalone BESS requires a different licensing analysis from PV + BESS.

Under the older licensing framework, ANRE expressly recognised a separate licence category for the commercial operation of storage installations that are not added to an existing production capacity; if storage is installed within an existing production capacity, the producer licence is modified to include the storage installation.

The current Order 6/2025 framework preserves the same basic distinction: standalone storage is a separate regulated activity, while storage added to generation capacity is handled through the production/storage authorisation and licence structure.

6.1 Establishment authorisation

For a standalone storage installation above the applicable threshold, an ANRE establishment authorisation is required.

The older regulation stated that ANRE does not issue authorisations for standalone storage installations if the maximum active power discharged into the grid is 1 MW or below, but notification obligations apply at start of works and after commissioning.

For large standalone BESS projects, the practical rule is:

If the BESS injects more than 1 MW into the grid, expect ANRE establishment authorisation.

The authorisation should match:

installed power
MWh capacity
point of connection
technology
project phasing
land
ATR
building permit
environmental act.

6.2 Operating licence

Before commercial operation, a standalone BESS project needs the relevant ANRE licence for commercial operation of a standalone storage installation.

The licence should support the intended business model:

charging from grid
discharging into grid
participation in wholesale markets
balancing services
congestion/flexibility services
ancillary services, if qualified
portfolio optimisation.

6.3 Licence mismatch risk

This is one of the most important legal risks.

A BESS owner may think it can do “everything” once it has a storage licence. That is not always correct.

Depending on the revenue model, it may also need:

8. Grid connection issues

Grid connection is the most valuable and most difficult part of standalone BESS development.

A standalone BESS is both a consumer and a producer from a grid perspective. It imports electricity when charging and exports electricity when discharging.

Therefore, the ATR must be reviewed for both directions.

8.1 Key ATR questions

The buyer or lender should check:

maximum injection capacity
maximum absorption capacity
voltage level
connection point
delimitation point
whether both charging and discharging are allowed
whether import and export rights are symmetric
whether grid charges apply differently for absorption/injection
whether connection is firm or constrained
whether there are limits on operating mode
whether reinforcements are required
whether the BESS can operate before reinforcements
whether the connection solution supports the revenue model.

Real case: A BESS project is marketed as 100 MW / 200 MWh. DD reveals the ATR allows 100 MW injection but only limited absorption, or imposes operational constraints. The project cannot perform the arbitrage strategy assumed in the model.

8.2 Connection agreement

A BESS project must have a grid connection agreement aligned with the ATR.

The GCA should be checked for:

connection tariff
payment schedule
connection works
reinforcement works
user versus operator scope
construction deadlines
energisation conditions
guarantees
termination triggers
responsibility for delays
ownership of connection assets.

For BESS, the GCA is especially important because connection works can be more complex where the project connects at 110 kV or near a Transelectrica substation.

El-Mor’s Bradu and Brazi projects illustrate the importance of grid location: both are planned at 203 MW / up to 800 MWh and intended to connect at 110 kV to substations operated by Transelectrica, with ATRs already obtained.

8.3 Capacity allocation for ≥5 MW BESS

From 2026, the capacity allocation mechanism becomes central.

11. Main legal risks for standalone BESS

Risk 1: The project is not actually standalone

A project may be marketed as standalone, but the documents show it is technically or legally dependent on a PV or wind project.

Check:

ATR
metering
land
connection point
operating logic
licence application
revenue model.

If the BESS cannot operate independently, it should not be priced as a standalone asset.

Risk 2: ATR covers injection but not absorption properly

For BESS, import capacity is as important as export capacity.

A project that cannot charge as assumed cannot earn as assumed.

Risk 3: Capacity allocation not secured

For projects of at least 5 MW, capacity allocation may be required. If capacity is not secured, the project is not RTB.

Risk 4: GCA not signed or connection works unclear

An ATR without a bankable GCA is not enough.

Risk 5: Fire safety underestimated

BESS fire risk can affect permitting, insurance, financing and local acceptance.

Risk 6: Revenue model assumes balancing income without qualification

A financial model based on FCR/aFRR/mFRR is not bankable unless the legal and technical qualification pathway exists.

Risk 7: Wrong licence category

Standalone storage licence is not the same as producer licence with co-located storage.

Risk 8: State aid restrictions ignored

Grant-funded BESS projects may have transfer, operation, procurement and clawback restrictions.

Risk 9: Technology change triggers permit updates

Changing chemistry, container type, PCS configuration, capacity or layout may require amendments.

Risk 10: Degradation and warranties not aligned with revenue

A 2-hour battery and a 4-hour battery have different legal and commercial risk allocation. EPC/OEM warranties must match revenue assumptions.

12. Due diligence checklist for standalone BESS

For an investor review, the diligence should be organised around a short number of decision points rather than a document dump.

Land and accessland rights, cable route, access road, safety perimeter and substation interface.
Permittingurbanism, environmental act, building permit, fire safety route and technology consistency.
GridATR, grid connection agreement, import and export capacity, guarantees and reinforcement exposure.
ANREestablishment authorisation, storage licence pathway and any additional market role.
Commercial modelarbitrage, balancing, aggregation, optimiser agreement, state aid and bankability of revenue assumptions.
Transaction protectionsconditions precedent, change-of-control, grid guarantee replacement, EPC/OEM transfer and lender step-in rights.

14. Investor conclusion

Standalone BESS in Romania is moving very quickly.

The investment case is real: renewable penetration is growing, system flexibility is scarce, price volatility creates arbitrage opportunities, balancing needs are increasing, and public support is now available for standalone storage.

But the legal complexity is also real.

A standalone BESS project must be analysed as a regulated electricity asset with four simultaneous identities:

a construction project — land, environmental, building permit, fire safety
a grid asset — ATR, GCA, capacity allocation, import/export rights
a licensed electricity activity — ANRE establishment authorisation and standalone storage licence
a market participant — arbitrage, balancing, aggregation, PRE/BRP, trader, optimiser and service contracts.

The biggest mistake is to look only at MW/MWh.

In Romania, a standalone BESS project is not bankable because the battery exists on paper. It is bankable when the project can legally charge, discharge, connect, trade, provide services, comply with safety requirements and monetise flexibility under Romanian market rules.

That is the real due diligence test.

Related reading and services

This article is part of the Romanian energy law content cluster. For the commercial route into a mandate, start with Energy Law in Romania and the Renewable Energy Legal Services page.

How Grigorescu Partners can help

Grigorescu Partners assists investors, developers, lenders and project owners with Romanian renewable energy projects, including legal due diligence, grid connection review, ANRE licensing, PPAs, BESS structuring, EPC and O&M contracts, project acquisitions and transaction execution.

If you are assessing a Romanian renewable energy project, the useful question is not only whether the project has documents. The useful question is whether those documents work together as a buildable, financeable and monetisable energy asset.